Construction progress payment application
Prepare progress payment applications with retainage and change orders.
| B | C | D | E | |
|---|---|---|---|---|
| 2 | Application for Payment | |||
| 3 | Maple Grove Dental, Suite 200 build-out · 4180 Maple Grove Rd, Suite 200, Hilliard, OH 43026 | |||
| 4 | Current payment due | $35,787.25 | ||
| 5 | Parties | |||
| 6 | To owner | Maple Grove Dental Group LLC | ||
| 7 | Owner address | 4180 Maple Grove Rd, Suite 100, Hilliard, OH 43026 | ||
| 8 | From contractor | Northline Renovation Co. | ||
Pay application
What’s included
- Pay application
- The signed summary: contract sum to date, completed and stored, retainage, previous certificates, payment due and balance to finish.
- Continuation sheet
- The schedule of values with previous, this period, stored, total, % complete, balance and retainage per line.
- Work entries
- Work completed and materials stored by application and line item.
- Applications and payments
- Each application’s retainage, amount due, payments and status.
- Change orders
- Change orders with amount, status and a match to the schedule of values.
- Settings
- Project, owner, contractor, contract sum, retainage rates and payment terms.
Questions
How is the current payment due worked out?
Completed work and stored materials to date, less retainage, gives the total earned. The previous application’s total earned less retainage is subtracted, and what is left is the current payment due.
Can retainage differ for stored materials, or drop later in the job?
Yes. Settings has separate rates for completed work and stored materials, and each application can override them, for example dropping to 5% once the job is half done. Earlier applications keep their own rates.
How do I add a change order?
Add it on Change orders and mark it Approved when signed; the contract sum changes. Then add a line for it on the schedule of values with its CO #, so you can bill against it. A check shows whether the two match.
Is this an official form?
No. It follows the usual layout of a contractor’s application for payment and continuation sheet. If your contract requires a specific form, copy the figures onto it.